Retread and Resurfacing Programme TEMPORARY TRAFFIC REGULATION ORDER 2022

Notice ID: MFN0643291

Notice effective from
11th February 2022 to 13th March 2022

BOURNEMOUTH, CHRISTCHURCH
AND POOLE COUNCIL VARIOUS ROADS - Retread and Resurfacing Programme TEMPORARY TRAFFIC REGULATION ORDER 2022
NOTICE IS HEREBY GIVEN that Bournemouth, Chrlstchurch and Poole Council, In exercise of Its powers under the Road Traffic Regulation Act 1984 as amended and the Traffic Management Act 2004, has made temporary traffic regulations, with the effects detailed below, to control traffic.
NOTICE IS HEREBY GIVEN that Bournemouth, Chrlstchurch and Poole Council, In exercise of Its powers under the Road Traffic Regulation Act 1984 as amended and the Traffic Management Act 2004, has made temporary traffic regulations, with the effects detailed below, to control traffic.
WHAT: The following roads on the anticipated dates as shown In the following schedule are to be closed to all vehicles. Suspension of parking -no parking no waiting at any time and no loading/unloading at any time will be permitted. Works to be undertaken from 8am to 6pm. Any vehicles left obstructing the works risk receiving a Fixed Penalty Notice and being removed
WHERE AND WHEN:
Stanpit, Christchurch  14th to 19th February 2022
From Purewell Cross
Roundabout to Coastguard Way, Including Junctions of Mudeford Lane, Queen's Road, Victoria Road and Ledbury Road. Other side roads within scope of works to have accessed controlled with
Traffic Managment_

Edward Road, Christchurch From B3059 Somerford Road to Southey Road  18th to 22nd February 2022 & 25th to 26th March 2022
Elphinstone Road, Highcliffe
From Chewton Common Road to Rlnwood Road Including closure of Junction with Highland Road 21st to 25th February 2022 & 25th to 26 March 2022

Elm Avenue, Christchurch From The Grove to Canberra Road 28th February to 1st March 2022 & 27th to 28th March 2022

St Anne's Avenue, Bournemouth Entire length  1st to 3rd March 2022 & 27th to 28 March 2022

Norwood Place, Bournemouth Entire length  3rd to 5th March 2022 & 27th to 28th March 2022 

Chessel Avenue, Bournemouth Entire length  4th to 7th March 2022 & 27th to 28th March 2022 

Mossley Avenue, Poole From Scott Road to Astbury Avenue including closure of junction with Hillside Road  6th to 9th March 2022 & 28th to 29th March 2022 

St Osmunds Road, Poole From a point Immediately south of Its Junction with Glengarlff Rd up to and
including the junction with Alton Road East also Including junction with Kings Avenue  8th to 11th March 2022 & 28th to 29th March 2022

WHY: First closure date: required for carriageway recycling with temporary surface Second closure date: required for laying of final running surface
ACCESS: Full Emergency access will be maintained, access to properties will remain depending on site safely DIVERSION: Via signed routes where applicable VIEW AT:

https://one.network/?tm=127226425

These arrangements may be amended/extended should works overrun or weather conditions delay operations. Restrictions may be In effect under this Order for up to 18 months and could be further extended with the approval of the Secretary of State.
The Council regrets any Inconvenience caused by this Traffic Order. ' Date authorised: 22 December 2021 Service Director: Transport and Engineering BCP Council CMc Centre, Boume Avenue, Bournemouth BH6 6DY