During the course of the coming week, Transport for Buckinghamshire will be carrying out work in the following places as part of the Strategic Highway Maintenance Programme.

As some activities depend on the weather, dates can change at short notice.

During this busy period, weekend working may take place in some places as indicated in the dates below.

Carriageway surfacing 

A418 Aylesbury Road, Haddenham – Low Lane to Haddenham Crossroads (Wednesday 17 July to Thursday 25 July)

 Conventional surfacing works taking place using a night time road closure in operation between 7pm to 6am      

A40, Knaves Beech, High Wycombe - Knaves Beech Roundabout to Watery Lane (Friday 26 July to Wednesday 7 August)

Conventional surfacing works taking place using a night time road closure in operation between 7pm to 6am     

Clayhill, Booker - Clay Lane to end (Monday 22 July to Tuesday 23 July)     

Micro-surfacing works taking place using a day time road closure in operation between 8:00am and 5pm

Newfield Way, Marlow - junction with Dedmere Court (Tuesday 23 July)

Micro-surfacing remedial works taking place using a day time road closure in operation between 8:00am and 5pm

Henley Road, Medmenham - SAS Roundabout to Ferry Lane (Tuesday 23 July to Wednesday 24 July)

Micro-surfacing remedial works taking place using a 4 way traffic signals in operation between 8:00am and 5pm  

River Road, Taplow - A4 to Ellington Road (Wednesday 24 July to Wednesday 24 July)     

Micro-surfacing remedial works taking place using a day time road closure in operation between 8:00am and 5pm

Ellington Road, Taplow - River Road to A4 (Wednesday 24 July to Wednesday 24 July)     

Micro-surfacing remedial works taking place using a day time road closure in operation between 8:00am and 5pm

Cedar Chase, Taplow - Rectory Road to end (Thursday 25 July)         

Micro-surfacing remedial works taking place using a day time road closure in operation between 8:00am and 5pm

Witheridge Lane, Penn - Crown pub to Clay Street (Thursday 25 July)

Micro-surfacing remedial works taking place using a day time road closure in operation between 9:30am to 3:30pm

Woodfield, Lacey Green - Main Road to end (Friday 19 July to Tuesday 23 July)     

Micro-surfacing works taking place using a day time road closure in operation between 8:00am and 5pm

Greenlands, Lacey Green - Main Road to end (Friday 19 July to Tuesday 23 July)  

Micro-surfacing works taking place using a day time road closure in operation between 8:00am and 5pm

Westlands Road, Lacey Green - Main Road to end (Friday 19 July to Tuesday 23 July)           

Micro-surfacing works taking place using a day time road closure in operation between 8:00am and 5pm

Meadow Rise, Lacey Green - Westlands Road to end (Friday 19 July to Tuesday 23 July)  

Micro-surfacing works taking place using a day time road closure in operation between 8:00am and 5pm

Roundlands, Lacey Green - Main Road to end (Friday 19 July to Tuesday 23 July) 

Micro-surfacing works taking place using a day time road closure in operation between 8:00am and 5pm

Eastlands, Lacey Green- Roundlands to end (Friday 19 July to Tuesday 23 July)   

Micro-surfacing works taking place using a day time road closure in operation between 8:00am and 5pm

Goodacres Lane, Lacey Green - Main Road to end (Friday 19th July to Tuesday 23 July)           

Micro-surfacing works taking place using a day time road closure in operation between 8:00am and 5pm

Clare Road, Prestwood - Wycombe Road to Blacksmith Lane (Tuesday 23 July to Wednesday 24 July)     

Micro-surfacing works taking place using a day time road closure in operation between 8:00am and 5pm

Aylesbury Road, Gt Missenden - Rignall Road to A413 (Wednesday 24 July to Thursday 25 July)     

Micro-surfacing works taking place using a day time road closure in operation between 8:00am and 5pm

Oxford Street, Lee Common - Lee Clump Road to Village Road (Thursday 25 July to Friday 26 July)    

Micro-surfacing works taking place using a day time road closure in operation between 9:30am and 3pm

Chartridge Lane, Chesham - Westdean Lane to Penn Avenue (Saturday 27 July to Wednesday 31 July)     

Micro-surfacing works taking place using a day time road closure in operation between 8:00am and 5pm

Roman Way, Bourne End - Waborne Road to Loddon Road (Saturday 20 July to Monday 22 July)

Ironwork adjustment works taking place using a localised traffic management in operation between 8:00am and 5pm

Brent Road, Bourne End - Loddon Road to end (Tuesday 23 July)

Ironwork adjustment works taking place using a localised traffic management in operation between 8:00am and 5pm

Cherwell Road, Bourne End - Roman Way to Waborne Road (Tuesday 23 July to Thursday 25 July)

Ironwork adjustment works taking place using a localised traffic management in operation between 8:00am and 5pm

Woodside, Flackwell Heath - Blind Lane to Woodside Avenue (Wednesday 24 July to Thursday 25 July)

Ironwork adjustment works taking place using 3 way traffic lights between 8:00am and 5pm       

Woodside Avenue, Flackwell Heath – Woodside to Woodside (Wednesday 24 July to Thursday 25 July)

Ironwork adjustment works taking place using 3 way traffic lights in operation between 8:00am and 5pm    

Drainage works

Peters Lane, Monks Risborough - Aylesbury Road to Kop Hill (Monday 8 July to Friday  26 July)           

Drainage works taking place using localised  traffic management in operation between 9.30 am and 3.00pm

Safety barrier repairs

Cotswold Way & Cheviot Close, High Wycombe - Brecon Way to Middlebrook Rd (Monday 22 July to Friday 2 August)     

Safety Barrier Work taking place using localised traffic management and Temporary Traffic Signals in operation between 9.30am and 3.30pm